Critical Lift Planning
Critical lifting is a project-defined review category, not a label this website awards from a calculator result. Obtain the applicable client, site and equipment requirements before deciding the review route. A single utilisation percentage or load weight is not a universal classification rule.

Identify the review triggers
Ask the project owner which conditions require additional review. Examples to discuss include multiple lifting devices, restricted clearance, consequences of load loss, unusual loads and complex interfaces. These are discussion prompts, not a complete standard or a substitute for the project’s criteria.
Make assumptions traceable
Record verified load data, configuration-specific chart references, rigging arrangement, site constraints and responsible reviewers. Explain what remains uncertain and how it will be resolved. Keep revision numbers and change descriptions so the team can distinguish the current reviewed arrangement from an earlier draft.
Set decision points
Document who checks readiness, how the team communicates and what changes require stopping and returning for review. Record the lift-specific stop-work criteria and confirm how the lifting team follows the site emergency procedures. The plan builder provides unsigned review spaces and a draft watermark; completing every field does not create approval. Agree the formal authorisation process with the responsible project parties.
Continue planning
Planning information, not lift approval. Confirm applicable Malaysian and project requirements with the responsible parties. No appointment or booking is made automatically.
References / Rujukan
Choose Malaysian sources or international background. Source links checked: . This is the check date, not the publication date.
Malaysia — JKKP / DOSH
Rujukan tempatan untuk menyusun pelan, peranan pasukan dan semakan jentera. Bezakan bahan latihan lama daripada peraturan dan proses semasa; semak keperluan yang terpakai dengan pihak projek dan JKKP.
- JKKP: Reka Bentuk Jentera Mengangkat Selain Lif, Eskalator dan Laluan Gerak
Official process guidance referring to the 2024 plant certificate-of-fitness regulations. Use this starting point to check applicable design-verification and machinery requirements, including scope and exclusions. A calculation or draft plan here does not establish registration or certificate status.
- JKKP: Kerja Mengangkat dengan Selamat — poster guidance
Safety-awareness guidance; not a consolidated legal text. Organise risk assessment, a lifting plan, suitable equipment, trained personnel and supervision. The team overview distinguishes the supervisor, crane operator, rigger and signalman roles.
- JKKP: Modul Latihan Penyelia Mengangkat (PDF, approximately 25 MB)
Historical training module dated 30 October 2017. Its planning chapter helps organise load information, crane arrangement, accessories and team responsibilities. The 2025 upload path is not the document date; check older legal references against current requirements.
No fixed inspection interval or universal critical-lift threshold is asserted here. Confirm the actual machine, personnel appointments and site requirements before the operation.
International — background and manufacturer information
- UK HSE: Planning and organising lifting operations
UK regulator guidance. Useful background on proportionate planning, responsibilities, supervision and foreseeable risks. It is not Malaysian legislation.
- Crosby: 2016 catalog sling-angle reference (PDF)
Manufacturer technical background, historical catalog. Use for the stated sling-angle relationship, not to select current equipment ratings. Confirm the applicable product instructions, hitch and configuration with the actual manufacturer.
- Liebherr: Crane Planner mobile
Manufacturer planning service. Configuration-specific crane information is separate from the manual arithmetic calculators on this website. We do not supply or infer its proprietary charts, and this link does not imply endorsement.
International material complements, but does not replace, applicable Malaysian requirements or project review. Tool-specific method references remain alongside each calculator.